October 2026 Newsletter

Council Refuses to Approve 80 Willow Road Project

At its meeting on Tuesday, September 29, the City Council made clear that, despite pressure from the California Attorney General’s Office and threats of litigation from developer N17, it would not direct staff to approve the proposed development at 80 Willow Road.
In recent weeks, the City Council has met nine times in closed session to discuss the project and the potential for litigation. I have been transparent and unwavering from the beginning about my position that the Council should not approve the project. The City Council’s response yesterday is the clearest indication yet that the City will continue to stand its ground, and I’m proud of the role I’ve played in steering the City Council to this position. As was stated during the meeting, “[We] believe the Attorney General’s conclusions are incorrectly reasoned and contrary to law.”
How We Got Here
The latest back-and-forth between the city, the state, and developer N17 began on July 29, when the California Attorney General’s Office sent the city a notice stating that it had violated AB 2011 and the Housing Accountability Act in its processing of the 80 Willow Road project. N17 followed with its own letter on August 3, notifying the city of its intent to pursue legal action.
Background on the 80 Willow Road Project
By way of background, the 80 Willow project seeks to rely on the state's Builder's Remedy provisions to develop more than 1.5 million square feet of office, hotel, retail, and residential space across four primary buildings, including a tower reaching approximately 450 feet. If constructed as proposed, it would be among the state’s tallest buildings and the only one not located in Los Angeles, San Francisco, or downtown San Diego.
What’s Next
What happens next is not entirely clear. N17 has threatened legal action against the city, and it may follow through with that threat. At least one pro-housing organization has also indicated that it may pursue litigation related to the city’s handling of the project.
We will have to see how these parties respond. Regardless of what happens next, I believe the city’s most important obligation is to carefully evaluate this project and protect the interests and safety of Menlo Park residents.
Congressman Sends Letter Requesting Federal Investigation
In another significant development, on September 23, Congressman Sam Liccardo, who represents Menlo Park, sent a letter to Treasury Secretary Scott Bessent requesting a federal review of the ownership and financing of 80 Willow Road and asking federal agencies to consider potential sanctions. You can read Congressman Liccardo’s letter here.
Potential Buyer Emerges
Several weeks ago, a well-resourced party with a serious interest in purchasing the 80 Willow Road property reached out to me. Since then, I have led discussions between the city and this potential buyer. Mayor Betsy Nash, who I’ve included in these discussions, has also been involved.
The potential buyer is very familiar with the property and values its historical significance. They have indicated that their intended use of the campus could be accommodated with only minimal interior modifications.
These discussions have focused on providing the potential buyer with information about the likely timeline and process for obtaining the city permits necessary for their intended use of the property. Of course, there is no guarantee that this party will ultimately acquire the property, but this represents a promising possibility for the future of the 80 Willow Road campus.
City Reviews Financial Analysis of Parking Lots Housing Proposals

At its September 29 meeting, the City Council reviewed a financial analysis of the three proposals to build housing on the downtown parking plazas. I requested this analysis after the developers presented their proposals to the City Council and all three essentially said the city would need to contribute funding if they were required to replace the public parking.
The developers’ statements represented a significant shift in the assumptions underlying this effort. Up to that point, the project had been understood to require no city contribution beyond transferring the three parking plazas to the selected developer.
More specifically, the report identifies funding gaps in the housing proposals ranging from approximately $20 million to $45 million. Closing these gaps, at least in part, will almost certainly require financial contributions from the city.
You can read the financial analysis and staff report here.
Coleman Avenue Pilot Project Becomes Permanent

At its September 22 meeting, the City Council voted 4-0 to make the Coleman Avenue Pilot Project permanent. As a result, the following traffic-calming and safety measures will remain in place:
Removal of parking from the north side of Coleman Avenue
A designated westbound bike lane toward Ringwood Avenue and a shared eastbound lane toward Willow Road
Stop signs on Coleman Avenue at Santa Monica Avenue
Speed humps on Coleman Avenue to reduce vehicle speeds, which will be upgraded from rubber to asphalt
When the Complete Streets Commission reviewed the pilot project, it recommended installing bollards along the bike lane. While bollards were not part of the original pilot, there was general support among the City Council for installing them, at least along portions of the bike lane, as part of future safety improvements. In my subsequent discussions with the City Manager, he was also supportive of this approach.
The City Council’s decision applies only to the portion of Coleman Avenue within Menlo Park city limits. Rubber speed humps have also been installed on the portion of the street in unincorporated San Mateo County. Any final decision regarding those speed humps or additional safety measures on the county portion of the street will be made by the San Mateo County Board of Supervisors.
You can learn more about the pilot project on this webpage.
Work Begins on Willow Road/Highway 101 Landscaping Project

Work on the landscaping project at the Willow Road/U.S. Route 101 interchange has officially begun. The first phase of work includes the installation of drainage facilities and erosion-control measures.
The nearly $2 million project will also include approximately 120 new trees, along with shrubs and other plants, mulch and ground cover, and a new irrigation system with lateral lines, meters and controllers. As part of the project, the contractor will also be responsible for a three-year plant establishment period following construction.
Caltrans is expected to maintain the landscaping once the project is complete. You can learn more about the project on the project website.
Laurel 5th Graders Visit City Hall, Lutticken’s Celebration, and Winter Preparedness

Laurel 5th Graders Visit City Hall – As part of their We the Kids! project-based learning program and social studies unit on the formation of the U.S. government, I recently hosted all Laurel School fifth graders at the City Council Chambers. It was an engaging session where I gave a presentation on local government, and Assemblymember Marc Berman joined us for a Q&A. We covered a wide range of topics, from taxes (they wanted to know what they’re actually used for) to code enforcement.
Celebrating Lutticken’s – On September 25, I joined a celebration organized by M-A Little League and Alpine Little League to honor Bob Lutticken and Lutticken’s following the announcement that the deli would close after 45 years in business. As part of the celebration, I presented a proclamation to the deli’s manager, Judy Congdon, recognizing Lutticken’s longtime support for the community, including sponsoring youth sports and routinely donating food to veterans.
Winter Preparedness Update – At its September 24 meeting, the San Francisquito Creek Joint Powers Authority staff presented an update on preparations for an expected strong El Niño season. These preparations include creek maintenance and debris removal, clearing storm drains, ensuring the availability of sandbags and temporary flood barriers, and coordinating emergency preparedness and activation plans. You can also learn more about the City’s storm and flooding preparedness at this webpage.
Community Events Roundup: Halloween Hoopla Parade and Carnival, Fourth Fridays Downtown, and Community Office Hours

Halloween Hoopla – This year’s Halloween Hoopla Parade and Carnival will take place on October 24 from 11 a.m. to 2 p.m. This Menlo Park tradition is a fun event for all ages, featuring Halloween-themed carnival games, prizes, candy, a craft table hosted by Cheeky Monkey, and performances by Menlo Park school bands.
Fourth Fridays Downtown – The Fourth Fridays concert series, which launched last year, continues to bring live music and activities to locations throughout downtown. The next event, taking place on October 23, will have a Halloween theme, and everyone is encouraged to come in costume. You can learn more at the Downtown Menlo Park website.
Community Office Hours – Join me every Saturday from 9:00–10:00 a.m. at Neighborhood Pizza Guy / Café Zoë in the Willows. Stop by to share your thoughts on city matters, ask questions, or simply say hello. No appointment is needed, though you’re welcome to message or email me in advance if you plan to attend.
Socials – You can connect with me on Facebook, Instagram, and LinkedIn.
This is a monthly newsletter from District 2 Councilmember Drew Combs. The purpose of this newsletter is to inform Menlo Park residents, and specifically those in District 2, about city issues. It joins other efforts to engage District 2 residents, including weekly community office hours. No public funds or resources are used to create or send this newsletter.